Twenty-One Kilometres and 1.1 Billion: The Price of the Second Line
Skjoldkraft puts figures on its alternative Intertie route on the eve of the status committee; Cree Council: “Better, and not enough”; Kaninaskum will ask for a consent condition on trapping grounds; committee sits this morning
The second line has a price.
On Wednesday evening Skjoldkraft filed its written evidence with the clerk of the Provincial Thing’s status committee. The papers say the alternative route for the Shield Intertie is twenty-one kilometres longer than the first. It would cost about VKR 1.1 billion more to build.
The committee sits this morning in Hokelgard. It will hear the Kaniapiskau Cree Council first, then Skjoldkraft, then officials from the Energy Ministry.
The Cree Council gave its answer to the second route on Wednesday afternoon. “It is better,” said Grand Chief Ruth Kaninaskum. “And it is not enough.”
The alternative keeps wider of both burial sites. But it still crosses two of the trapping grounds the Council has named. Ms Kaninaskum said she would ask the committee to add a condition: no line through a named trapping ground without the consent of the families who use it.
“We are not asking the committee to pick a line,” she said. “We are asking it to say who must agree.”
First Minister Erik Halvorsen spoke briefly about the Intertie on Wednesday. He said the Government would “take the committee’s finding as it comes”.